|
|||||
Getting the Sponsor You NeedRule 4 - In the absence of information, executives still make decisionsSince the 1970's, experts in executive decision-making such as Henry Mintzberg (The Nature of Managerial Work, Harper & Row, 1973) proved that executives prefer "informal" modes of communication such as face-to-face discussions and meetings to "formal" modes of communication such as reports, metrics and statistics. With the increasing pressures of competition, deregulation, takeovers, mergers and economic rationalism, most executives that we work with are under substantially more pressures than those studied in the 1970's by Mintzberg. As a result, their reliance on informal and fast communication has increased. For you as a project manager, this is an important understanding. Your executives will make decisions based on either good information or bad data. You decide what they get! It has been our experience that the typical executives in project sponsor roles operate in an information vacuum. One example of this Rule is in the approval of new projects. Many of the organisations, with which we are familiar, have established "filters" for executive information. For example, the senior executive committees are only given information on the really large projects. One company we have worked with had a guideline that senior executives only approved and reviewed projects over $5 million dollars. As a result of this guideline, the executive Steering Committee had information on only 12 projects. There was over 200 other projects underway in that IT organisation that was not reported on at all. The "smaller" projects were consuming over 50% of the IT resource. So, it is completely understandable, given the information vacuum that this executive committee worked in, that they would continuously approve new IT projects when there were no IT resources to allocate to the project. After all, they were only seeing half the picture. Another example of this Rule is in the area of project reporting. In discussions with a number of executives, we have determined that most of them do not read the complex project status that are sent to them on a monthly basis (see Figure 3). Worse, many of these executives report to us that even when they do read them, they either don't understand them or don't believe them! After all, do you?
Fig. 3 - Data not informationAs a project manager, you must learn to communicate to your project sponsor in short, information-rich messages. In general, most project sponsors want to know two things. The first is "is the project OK or not OK?" (what is meant by "OK" would be determined by the specific agreed Business Case or Project Charter developed at the beginning of the project). The second piece of information is "if not OK, what must the sponsor do to assist the project manager is fixing it up?" This Rule also applies to issues of business alignment, cost-benefit analysis, project risk management, estimation and other critical project management information. For example, if the project risk analysis, benefits analysis and estimation has been done poorly, it is rare that a senior business executive would have either the time, information available or expertise to discover the errors (see Rules 5 and 6). In effect, faced with poorly developed and presented data, the executive will simply operate on "gut feel", informal information and organizational political concerns to make the project decision. |
| << Rule 3 | Rule 5 >> | |||
|
copyright: thomsett INTERNATIONAL 2008 | contact |
||||