TI logo
Home

Our Company

Public Workshop Schedule

In-house Delivery and Consulting

Workshop Descriptions

Site Map

Articles

 

Track 2000

Problem 3 -Scheduling tool implementation

Some scheduling tools allow the default linear completion method to be over-ridden. For example, in Microsoft Project, you can use an actual effort option which enables you to enter 20% complete on Day 3 [curve A]. However, because of the difficulties of programming these tools, once you enter a 20% complete figure, the task is then shown to be 40% over schedule [as it "should" have been 60% complete].

Alternatively, some tools allow options such as the 0/100% complete method which involves a binary state for tasks - either they are completed or not started. Another option involves all tasks having been commenced being treated as default 50% complete until they are finished. Clearly, these options do not recognise the complex patterns of completion and, in reality, are poor compromises.

As a result, most scheduling tools cannot allow for real world tracking.

<< Back Next >>

copyright: thomsett INTERNATIONAL 2006 | contact