Case 5: Behind schedule, over cost and fine

In Figure 9, a project has a high Return on Investment [$150,000] based on estimates of development costs of $100,000 and suport costs of $100,000 but faced with potential development cost blowouts the team has two options.

  • In Option 1 which is similar to Case 4, the team can degrade the quality of the system. This will result in the support costs being blown out from $100,000 to $200,000 and the expected Return on Investment being reduced to $50,000.

  • Option 2 is that the team allows the development costs to blowout by 30% to $130,000 and to delay shipping by a few months. The support costs are maintained at $100,000 but expected benefits are reduced to $300,000.

Option 2 results in a better Return on Investment of $70,000 than Option 1. However, the team would be shown as behind schedule and over budget in traditional tracking reports.

Fig 9. Behind Schedule, Over Cost and Fine